1147.14 TEMPORARY CONSTRUCTION TRAILERS/OFFICES.
   (a)   Temporary Construction Trailers/Offices. Temporary construction trailers/offices may be permitted in any District during the construction of building(s) and site improvements provided the following regulations are met. A Zoning Clearance Permit shall be obtained prior to installing and utilizing the temporary construction trailer/office.
      (1)   The temporary trailer/office shall be prohibited from being located in the right-of-way and shall be setback a minimum of ten (10) feet from the right-of-way line.
      (2)   In all Districts, except the AM, the temporary trailer/office shall only be permitted for a period of two (2) years in any calendar year. If additional time is necessary due to a delay in construction, the applicant shall seek an extension from the Board of Zoning Appeals. Due to the intensity of use and length of construction time for sites within the AM District, this time frame does not apply to temporary construction trailers/offices in the AM District. (Ord. 15-23. Passed 8-14-23.)