Unless otherwise specified in the action to permit a structure to be relocated, the applicant's right to exercise such permission shall become null and void ninety days from the effective date of such action if applicant has failed to commence work as to the relocation. However, one extension of time only to commence work may be granted by action of the planning commission if so requested and if the commission feels such extension is justified. Such extension of time to commence work shall not be for any period of time in excess of sixty days.
(Ord. 28 § 1 (part), 1961; prior code § 9511).