(A) Development orders and development permits are designated preliminary or final under the development review process, as delineated below:
Type I Preliminary (No Concurrency Test. Capacity Reservation Not Available.)
1. Variance
2. Abandonment
Type II Preliminary (Internal Concurrency Test. Capacity Reservation Optional.)
1. Plan amendment
2. Rezoning
Type III Preliminary (Concurrency Test/Encumbrance. Capacity Reservation Available at Applicant's Option.
1. Preliminary subdivision plan
2. Conditional use
Type IV Final (Concurrency Test/Capacity Reservation Required)
1. DRI
2. All development permits except as exempted in § 161.08
3. Final site plan
4. Final subdivision plan and plat
(B) Each applicant for a Type IV final development order, except as provided in § 161.08 shall pay the appropriate concurrency reservation fees and apply for a Certificate of Capacity.
(C) Each applicant for a Type II or Type III Preliminary Development Order: Concurrency option, except as provided in § 161.08 shall elect one of the following options:
(1) Pay the capacity reservation fee and apply for a certificate of capacity; or
(2) Execute a nonconcurrency affidavit.
(Ord. 633, passed 2-18-93)