(A) (1) Any permit issued in accordance with this chapter shall be valid for a period of two years from the date of issuance. Any permit requiring a foundation inspection shall be commenced and have a foundation inspection completed and approved within three months of permit issuance.
(2) All other permits shall be revoked and rendered null and void if construction, alteration, modification, remodel or repair defined under said permit is not commenced within six months of issuance. If any question arises, it shall be the responsibility of the developer, builder, agent or owner to prove work on any permit under this paragraph was commenced with the required six-month period.
(B) A permit is valid for a period of two years from date of issuance subject to provisions of § 151.040. All work must be completed within the two-year period or the permit must be renewed.
(Prior Code, § 151.018) (Ord. passed 11-2-1970; Ord. 2158, passed 9-12-2006)