(A) Work in progress shall be subject to inspection by the enforcement authority or his or her designate.
(B) There shall be a minimum of one inspection at each of the following stages of work:
(1) Rough-in service.
(2) Rough-in wiring.
(3) Final inspection.
(C) Additional inspections may be made as deemed necessary by the enforcement authority.
(D) Following the rough-in inspection, the enforcement authority shall inspect the meter base for the purpose of informing the appropriate utility that the installation has received approval for hook-up of electrical service. The enforcement authority shall notify the appropriate utility within 72 business hours of approval. Provided, however, this provision shall not be construed in any way as granting the enforcement authority the authority to order the appropriate utility to hookup electrical service to any installation.
(E) Charges for electrical inspections will be established by ordinance by the Common Council.
(F) Inspections shall be made within two working days of request except Saturday, Sunday, and holidays.
(Ord. 5560, passed 11-3-86; Am. Ord. 6477, passed 4-23-07) Penalty, see § 150.99