§ 54.071 OPERATION AND MAINTENANCE AGREEMENT.
   (A)   In general.
      (1)   Prior to the conveyance or transfer of any lot or building site to be served by a structural BMP pursuant to this chapter, and prior to issuance of any permit for development or redevelopment requiring a structural BMP pursuant to this chapter, the applicant or owner of the site must execute an operation and maintenance agreement that shall be binding on all subsequent owners of the site, portions of the site, and lots or parcels served by the structural BMP, until the transference of all property, sites, or lots served by the structural BMP, the original owner or applicant shall have primary responsibility for carrying out the provisions of the maintenance agreement.
      (2)   The operation and maintenance agreement shall require the owner or owners to maintain, repair and if necessary, reconstruct the structural BMP, and shall state the terms, conditions, and schedule of maintenance for the structural BMP. In addition, it shall grant to the city a right of entry in the event that the Stormwater Administrator has reason to believe it has become necessary to inspect, monitor, maintain, repair or reconstruct the structural BMP; however, in no case shall the right of entry, of itself, confer an obligation on the city to assume responsibility for the structural BMP.
      (3)   The operation and maintenance agreement must be approved by the Stormwater Administrator prior to plan approval, and it shall be referenced on the final plat and shall be recorded with the county Register of Deeds upon final plat approval. A copy of the recorded maintenance agreement shall be given to the Stormwater Administrator within 14 days following its recordation.
   (B)   Special requirement for homeowners' and other associations. For all structural BMPs required pursuant to this chapter and that are to be or are owned and maintained by a homeowners' association, property owners' association, or similar entity, the required operation and maintenance agreement shall include all the following provisions:
      (1)   Acknowledgment that the association shall continuously operate and maintain the stormwater control and management facilities.
      (2)   Establishment of an escrow account, which can be spent solely for sediment removal, structural, biological or vegetative replacement, major repair, or reconstruction of the structural BMPs. If structural BMPs are not performing adequately or as intended or are not properly maintained, the city, in its sole discretion, may remedy the situation, and in such instances the city shall be fully reimbursed from the escrow account. Escrowed funds may be spent by the association for sediment removal, structural, biological or vegetative replacement, major repair, and reconstruction of the structural BMPs, provided that the city shall first consent to the expenditure.
      (3)   Both developer contribution and annual sinking funds shall fund the escrow account. Prior to plat recordation or issuance of construction permits, whichever shall first occur, the developer shall pay into the escrow account an amount equal to 15% of the initial construction cost of the structural BMPs. Two-thirds of the total amount of sinking fund budget shall be deposited into the escrow account within the first five years and the full amount shall be deposited within ten years following initial construction of the structural BMPs. Funds shall be deposited each year into the escrow account. A portion of the annual assessments of the association shall include an allocation into the escrow account. Any funds drawn down from the escrow account shall be replaced in accordance with the schedule of anticipated work used to create the sinking fund budget.
      (4)   The percent of developer contribution and lengths of time to fund the escrow account may be varied by the city depending on the design and materials of the stormwater control and management facility.
      (5)   Granting to the city a right of entry to inspect, monitor, maintain, repair, and reconstruct structural BMPs.
      (6)   Allowing the city to recover from the association and its members any and all costs the city expends to maintain or repair the structural BMPs or to correct any operational deficiencies. Failure to pay the city all of its expended costs, after 45 days written notice, shall constitute a breach of the agreement. In case of a deficiency, the city shall thereafter be entitled to bring action against the association and its members to pay, or foreclose upon the lien hereby authorized by the agreement against the property, or both. Interest, collection costs, and attorney fee shall be added to the recovery.
      (7)   A statement that this agreement shall not obligate the city to maintain or repair any structural BMPs, and the city shall not be liable to any person for the condition or operation of structural BMPs.
      (8)   A statement that this agreement shall not in any way diminish, limit, or restrict the right of the city to enforce any of its ordinances as authorized by law.
      (9)   A provision indemnifying and holding harmless the city for any costs and injuries arising from or related to the structural BMP, unless the city has agreed in writing to assume the maintenance responsibility for the BMP and has accepted dedication of any and all rights necessary to carry out that maintenance.
(Ord. 15-01, passed 1-15-2015)