4-2-2: PERMIT FEES:
The fees for all permits as may be required by this title are hereby established as follows:
PERMIT FEE SCHEDULE
Volume computation: Volume shall be computed on the exterior dimensions of the building, and shall include all space above the lowest level of the foundation wall and below the ceiling of the uppermost floor.
Additions and incidental or accessory buildings:
 
$35.00 per 1,000 cubic feet, minimum fee
$200.00
Air conditioning:
 
Commercial or industrial, $125.00 per 3,000 square feet or major fraction thereof, with minimum of
$125.00
Single-family residential, per unit
$75.00
Alterations/remodeling:
 
On which the cubic feet basis of measurement is not practicable $12.00 per $1,000.00 of estimated cost of construction, minimum fee
$100.00
Certificate of occupancy:
 
Single-family residential, per unit
$100.00
Additions, incidental or accessory buildings
$75.00
Nonresidential $0.15 per square foot
Calculated
Miscellaneous
$50.00
Code compliance bond:
 
50 percent of principal building permit fees, with a minimum of
$100.00
Completion bond:
 
Original
$5,000.00
Upon first renewal of permit
Additional $5,000.00
Upon second renewal of permit
Additional $10,000.00
Contributions - residential:
 
Residential subdivisions platted after May 19, 2020 shall pay an impact fee to the Village of Kildeer per lot paid at the time of building permit issuance.
$5,000.00
Residential subdivisions platted after March 4, 1996: See section 6-3-13 of this code for provisions regarding dedication of school land or payment of fees in lieu thereof.
 
Residential subdivisions platted prior to March 4, 1996: The following amounts are applicable per lot, paid at the time of building permit issuance. Said fees are to be used by the school districts in the same manner and for the same purpose as set forth in section 6-3-13 of this code.
 
Elementary school district
$450.00
High school district
$250.00
Culvert and driveway:
 
Driveway
$100.00
Per culvert
$75.00
Decks:
 
$0.30 per square foot, with a minimum fee of
$200.00
Electrical work:
 
Commercial or industrial per 3,000 square feet or major fraction
$125.00
New construction, residence
$200.00
Remodeling, alteration, etc.
$100.00
Examination of plans/processing fee:
 
The minimum fee for examination of plans shall be $75.00. The fee for plans for construction shall be computed at the rate of 0.1 percent of the total cost of construction. A processing fee for roofs, siding, windows, doors, water heaters, furnace replacements and A/C replacements shall be $25.00. This fee shall not be refundable.
 
Excavation:
$200.00
Generator:
$200.00
Heating:
 
A/C condenser replacement
$75.00
Furnace replacement
$75.00
Single-family residential, per unit
$125.00
Commercial or industrial (per 3,000 square feet or a fraction thereof)
$125.00
Other consultant/agency fees:
 
Expenses incurred by the village for plan review or inspections shall be included with the permit fees as applicable. Other consultants/agencies include the village engineer, village arborist, wetland consultant, fire district, stormwater management consultant, and any other specialized consultants.
As billed
Patio
$100.00
Plumbing:
 
3 fixtures or less, minimum fee
$100.00
Each additional fixture
$30.00
Gas line for fire pit, grill (for each line)
$100.00
Water heater replacement
$75.00
Pool enclosures:
 
Minimum fee
$100.00
Each linear foot over 200
$0.30
Principal building and initial build out of space within a shell building:
 
Less than 10,001 cubic feet
$500.00
More than 10,001 cubic feet - $400.00 plus $35.00 for each 1,000 cubic feet in excess of 10,001
Calculated
Incidental and accessory buildings erected at the same time shall be included in the same permit and charged at the appropriate rate.
 
Reinspection fee:
 
Where a reinspection is required, or where extra nonscheduled inspections are requested, per inspection:
 
Residential
$100.00
Commercial
$150.00
Renewal fee:
 
For first 6 months
$500.00, plus an additional $5,000.00 completion bond
For second 6 months
$5,000.00, plus an additional $10,000.00 completion bond
Thereafter
See section 4-2-11 of this chapter
Repairs and alterations:
 
$12.00 per $1,000.00 of estimated costs of construction, minimum fee
$100.00
New siding, roofing, windows, doors, each at
$75.00
Sewage disposal:
 
Sewage system repair, field only
$75.00
Sewage system repair, tanks only
$75.00
Sewer service inspection fee
$75.00
System designed for commercial or industrial uses, including grease trap
$500.00
Sheds:
$150.00
Signs:
 
Illuminated signs
$200.00, plus $1.00 per square foot
Nonilluminated signs
$160.00, plus $1.00 per square foot
Temporary signs
$100.00
Permit penalty: If a person installs, allows to be installed, or attempts to install any sign without first securing a permit, the fee for the sign permit shall be 100 percent more than otherwise provided for by this chapter.
 
Renewal fees: Sign permits shall expire June 30 of each calendar year. The building department shall inspect annually, or at such other times as it deems necessary, each sign or other advertising structure regulated by this chapter for the purpose of ascertaining whether it is secure and safe, and whether it is in need of removal or repairs. To meet the expense of such inspection, each permittee shall pay to the village collector annually on or before July 1 a renewal fee:
 
Illuminated sign
$200.00
Nonilluminated sign
$100.00
Sports courts (each court)
$400.00
Storm sewer:
 
Connection inspection
$75.00
Swimming pools:
$450.00
Telecommunications facilities/towers (per foot annually)
$2.00
Water supply:
 
Drilling or digging of well
$75.00
Supply system other than residential use (up to 500 gallons' storage)
$100.00
Supply system other than residential use (over 500 gallons' storage)
$500.00
Wrecking (per building)
$150.00
Note: Any construction work started without first securing a permit shall be subject to a penalty fee in the amount of 150 percent of the permit fee in addition to the usual fee to cover the cost of extra inspections involved, with a minimum fee of $150.00.
 
It further shall be unlawful to occupy a residence without having, prior thereto, secured an occupancy permit and the penalty therefor shall be $100.00 per day of violation.
 
 
 
 
(Ord. 16-O-018, 6-21-2016; amd. Ord. 20-O-011, 5-19-2020)