1106.15 TEMPORARY STRUCTURES.
   (a)   Temporary structures must be removed within fourteen (14) days.
   (b)   No temporary structure can be erected for more than fourteen (14) days in a ninety (90)-day period.
   (c)   The applicant may obtain a permit from the Community Development Director to exceed the 14-day limit. The Director's decision will be based upon the temporary structure's impact upon the community and concerns regarding any potential safety hazards.
   (d)   A temporary structure (such as a tent or canopy) erected in the back yard of a residence that complies with all required setbacks and is not being used for any business purpose is not subject to the fourteen (14) day time limits.
   (e)   In addition, at the discretion of the Building Official, any structure in place for more than sixty (60) days, regardless of whether such structure is legal, may be deemed a permanent structure, subject to all the rules and requirements of a permanent structure, including a site plan and permits.
   (f)   Temporary structures for use incidental to construction work may be erected in any of the zoning districts. Such temporary building or buildings must be removed upon completion or abandonment of the construction work.
(Ord. 2021-057. Passed 6-16-21.)