§ 51.24  CONNECTION REQUIREMENTS.
   From and after 6-1-1979, all applicants for water and sewer connections, in addition to other requirements of §§ 51.20 et seq., will comply with the following requirements.
   (A)   There will be installed on each water line a cut-off valve on the owner side of the water meter box which will provide a means of stopping the flow of water without the necessity of using the town's valves in the meter box.
   (B)   There will be installed on each sewer line a sewer clean-out valve.
   (C)   All valves mentioned in the divisions (A) and (B) above must be approved by the Building Inspector for the Town of Kenly prior to the town's cutting on water to the premises.
   (D)   On new construction projects, the contractor or someone on his or her behalf must post a water deposit as would be required for an owner of the property prior to the town's cutting on water to the project.
(Ord. 51, passed 5-7-1979)  Penalty, see § 51.99