(A) A tree permit application shall be submitted to the Village Manager on a form provided by the Village Manager setting forth or otherwise providing the information described in this section, concurrent with the submission of any permit application for, and prior to commencement of, any construction activity:
(1) The name and address of the applicant;
(2) The owner’s name and address and the owner’s signed consent to the application if the applicant is not the owner;
(3) The street address or legal description of the lot on which the construction activity will occur and the lot or property on which the protected tree or heritage tree is located, if different;
(4) A description of the size (DBH), genus, species and condition of the protected tree or heritage tree to be damaged or removed;
(5) A brief explanation of the reasons necessitating impact on, damage to or removal of the protected tree or heritage tree, or a statement certifying that no impact on, damage to or removal of a protected tree or heritage tree will occur;
(6) A construction activity protection plan, if applicable, in accordance with § 150.166;
(7) A description or depiction of the size and location of any utility facility located, or proposed to be located, on the lot or any adjacent property; and
(8) Any other data and information as the Village Manager shall deem necessary to allow full and fair consideration of the tree permit application.
(B) Any person submitting an application for a permit or approval to perform any work pursuant to codes and ordinances of the village or other law may be required to certify that the work under the permit or approval is not construction activity under this subchapter. In the event that any certification is found by the Village Manager or Building Commissioner to be untrue or incorrect, all work included in the permit or approval may be stopped until an application is filed pursuant to this subchapter and any appropriate permits or authorizations are issued by the village.
(Ord. 945, passed 10-11-2005)