The application for a preliminary plan approval shall be considered officially filed on the day it is received by the Commission and shall be so dated. The application shall include the preliminary plan, the preliminary plan questionnaire and the application form for preliminary plan approval. The Commission staff shall notify the subdivider of any additional data required and Commission action may be delayed until said data is received. Filing shall be at least 14 days prior to the regular Commission meeting at which the plan is to be reviewed. Any plat received less than fourteen days prior to the regular Commission meeting shall be discussed at the succeeding regular Commission meeting. A fee, as specified in § 151.175 of this chapter, shall be required for the filing of the preliminary plan.
(Ord. 537, passed 7-19-90)
Cross-reference:
Preliminary Plan Questionnaire, see Appendix, § 3
Application for Preliminary Plan Approval, see Appendix, § 4