§ 8 METER AND SERVICE BRANCH CHARGES.
                  METER AND SERVICE BRANCH CHARGES
Minimum requirement for properties less than 1 acre
Minimum requirement for properties less than 1 acre
5/8" x 3/4" Meter and Tap
Cost
Sales Tax
Sub-Total
Overhead
TOTAL
Short
3/4" tap/branch to property line*
$1,445.36
$1,445.36
$433.61
$1,878.97
5/8" x 3/4" meter
$235.60
$235.60
$70.68
$306.28
W-3 Ford meter box and lid
$284.64
$19.92
$304.56
$91.37
$395.93
#502 yoke, angle valves and expansion
$152.83
$10.70
$163.53
$49.06
$212.59
24" meter box
$85.94
$6.02
$91.96
$27.59
$119.54
   TOTAL
$2,204.37
$36.64
$2,241.01
$672.30
$2,913.31
Capital Improvement Fee
$3,000.00
Short Tap
$5,913.31
*
Long
Tap/branch - additional
$700.80
$700.80
$299.20
$1,000.00
Long Tap
$6,913.31
Minimum requirements for 1 acre lot
   1" Meter and Tap
Cost
Sales Tax
Sub-Total
Overhead
TOTAL
Short
1" tap/branch to property line*
$1,638.84
$1,638.84
$491.65
$2,130.49
1" meter
$326.60
$295.00
$88.50
$383.50
W-3 Ford meter box cover
$283.48
$19.84
$303.32
$91.00
$394.32
#504 yoke, angle valves and expansion
$242.62
$16.98
$259.60
$77.88
$337.48
24" meter box
$87.10
$6.10
$93.20
$27.96
$121.16
   TOTAL
$2,578.64
$42.92
$2,589.96
$776.99
$3,366.95
Capital Improvement Fee
$5,000.00
Short Tap
$8,366.95
*
Long
Tap/branch - additional
$723.00
$723.00
$277.00
$1,000.00
Long Tap
$9,366.95
Minimum requirements for 3 acre lot
1-1/2" Meter and Tap
Cost
Sales Tax
Sub-Total
Overhead
TOTAL
Short
1-1/2" tap/branch to property line*
$2,070.28
$2,070.28
$621.08
$2,691.36
1-1/2" meter
$528.60
$423.00
$126.90
$549.90
#30 Monitor meter box cover
$446.49
$31.25
$477.74
$143.32
$621.07
1-1/2 meter setter and fittings
$986.09
$69.03
$1,055.12
$316.53
$1,371.65
30" meter box
$261.41
$18.30
$279.71
$83.91
$363.62
   TOTAL
$4,292.87
$118.58
$4,305.85
$1,291.75
$5,597.60
Capital Improvement Fee
$9,000.00
Short Tap
$14,597.60
*
Long
Tap/branch - additional
$782.00
$782.00
$218.00
$1,000.00
Long Tap
$15,597.60
Minimum requirement for 5 acre lot
2" Meter and Tap
Cost
Sales Tax
Sub-Total
Overhead
TOTAL
Short
2" tap/branch to property line*
$2,555.11
$2,555.11
$766.53
$3,321.64
2" meter
$658.60
$613.00
$183.90
$796.90
#30 Monitor meter box cover
$636.48
$44.55
$681.03
$204.31
$885.34
Meter setter and fittings
$1,130.62
$79.14
$1,209.76
$362.93
$1,572.69
30" meter box
$284.88
$19.94
$304.82
$91.45
$396.27
   TOTAL
$5,265.69
$143.64
$5,363.73
$1,609.12
$6,972.85
Capital Improvement Fee
$15,000.00
Short Tap
$21,972.85
*
Long
Tap/branch - additional
$879.00
$879.00
$121.00
$1,000.00
Long Tap
$22,972.85
 
Prices effective 1-1-2018
(Ord. 05-08, passed 4-21-08; Am. Ord. 07-13, passed 11-18-13; Am. Ord. 19-17, passed 12-18-17)