§ 54.070  STORM WATER VIOLATIONS AND REPORTING.
   Storm water management plan, NPDES permit and non-permit related storm water violations include, but are not limited to:
   (A)   Commencing site grading or preparation work without first having obtained approval from the City Engineer of all applicable permits;
   (B)   Non-compliance with the requirements or conditions attached to an approved SWPPP of an NPDES/SDS storm water permit for construction activity, storm water management plan or other standards established by the City Engineer, under authority of the city;
   (C)   The causing or allowing of a prohibited discharge in the city storm water system, a natural watercourse, storm water easement, stream or river;
   (D)   Failure to remove sediments transported or tracked onto city streets by vehicles or construction traffic within 24 hours of it being deposited on the street;
   (E)   Failure to install and maintain the erosion control measures (BMPs) on a construction site as outlined in the approved SWPPP and its amendments or other standards established by the City Engineer, under authority of the city;
   (F)   Other violations or issues as noted or described throughout this chapter;
   (G)   The causing or allowing of an illicit connection to the city storm water management system; and
   (H)   The City Engineer shall document the reporting of a violation in writing.
(2004 Code, § 54.040)  (Ord. 07-0462, passed 4-24-2007; Ord. 15-0737, passed 3-24-2015)