1153.02 EXPIRATION OF ZONING APPROVAL.
   Any zoning approval granted by the Planning and Zoning Commission shall expire if work thereunder is not in compliance with the following:
   (a)   If no work under the approval plan is commenced within one (1) year after the issuance of the approval (e.g., ground shall have been broken).
   (b)   If, after work has been commenced, all work to be performed under approval is not completed within twenty-four (24) months after issuance of the approval.
   (c)   A person may obtain a one-time six-month extension of the approval upon a showing, satisfactory to the Building Inspector, that work on the project will be completed within the extension period.
   (d)   If approval has been expired for a period of six (6) months or less, the applicant may renew the approval for a period to be determined by the Planning and Zoning Commission upon a showing, satisfactory to the Commission that work on the project will be completed within the extension period, provided no changes have been made in the original plans and specifications for such work. If an approval has been expired more than six (6) months, or if work has deviated from the approved plans, the then applicant must seek a new approval from the Planning and Zoning Commission. (Ord. 2023-6. Passed 6-15-23.)