(a) The Executive Parkway East Pump Station Sanitary Sewer Service Area is an area bounded by State Route 303 to the south, District 6 including Western Hudson Gateway and Hudson Executive Office Park, River Oaks Subdivision Phases III through VI and Oak Point Commons Subdivision. A map of the Executive Parkway East Pump Station Sanitary Sewer Service Area is attached to Ordinance 07-40 as Exhibit 1.
(b) The purpose of the Executive Parkway East Pump Station Capital Cost Recovery Program is to recover, through connection fees, the estimated incremental costs for the construction of the Executive Parkway East pump station to service the incremental increased flow from nonresidential users.
(c) An Equivalent Residential Unit ("ERU") is the estimated flow from a residential unit, being 400 gallons per day, as outlined in the Ohio Environmental Protection Agency (EPA) Suggested Sewage Flow Guideline.
(d) At the time of connection to sanitary sewers in the Executive Parkway East Pump Station Sanitary Sewer Area, the owner of a property shall pay for nonresidential connections an additional connection fee of four hundred eighteen dollars ($418.00) for each equivalent residential unit of the property owner based upon the property owner's proposed use. The Ohio EPA Suggested Sewage Flow Guideline shall be used for calculation of ERUs, a copy of which is attached to Ordinance 07-40 as Table II. The connection charge shall be used to reimburse the Municipality for the Executive Parkway East Pump Station Capital Cost Recovery Program.
(Ord. 07-40. Passed 5-2-07.)