(a) (1) A plumbing permit shall be issued upon an application in writing to the office of City Clerk on a form or forms provided for the purpose.
(2) This application shall, among other things, disclose the following:
(A) The name of the owner of the lot or tract of ground;
(B) The location of the building or structure;
(C) The plumbing work proposed;
(D) The class of occupancy;
(E) The class of construction;
(F) The kind of materials to be used;
(G) The estimated cost of the work;
(H) The date work will commence;
(I) Expected date of completion;
(J) Name and address of plumber, plumbing contractor or contractors doing the work; and
(K) Such other information as may be pertinent to the issuance of the required permit.
(b) An application for a plumbing permit shall be signed by the owner or his or her duly authorized agent, or a plumber or plumbing contractor licensed by the city. If the application is made by the owner or his or her agent, it shall contain the name or names of the licensed plumber, plumbing contractor or contractors doing the work described, or a plumbing permit may be issued to the owner upon his or her application disclosing satisfactory evidence that the proposed work will be performed by the owner, himself or herself and not by a licensed plumber or plumbing contractor, and likewise subject to the final approval of the Plumbing Inspector for work performed.
(c) Upon approval of the completed application and a determination that a permit should be issued, the Chief Building Official or his or her assistant shall issue a permit to the owner or contractor authorizing the plumbing work covered by the application.
(d) Any permit issued under this section shall be valid and subsisting for a period of not more than six months from the date of issuance unless the permittee shall have commenced, within the period so limited, the plumbing work authorized by such permit. Plumbing work commenced for the purpose of this section shall mean the beginning of plumbing work other than the preparation of plans or the letting of a plumbing contract.
Whenever an application for a plumbing permit is made, the Chief Building Official or the Plumbing Inspector may, if he or she finds it necessary to determine whether work described in the application will comply with the laws pertaining to such work, require that the applicant file a written description or drawing of the proposed plumbing construction as may be prepared for the purpose. If such drawing or description is insufficient for the purposes of determining whether a permit should be issued, the Chief Building Official or the Plumbing Inspector may require the applicant to file complete architectural and engineering plans and specifications for such building or construction, or any part thereof, as may be necessary for the Inspector to determine compliance with this article. The filing of such plans and specifications and the approval thereof in connection with an application for a permit shall not in any way affect the authority of the city to deny or issue a permit, or to inspect any plumbing work for conformity with this article.
The fee for a plumbing permit, as set by the governing body, shall be required to obtain a permit where the total estimated cost, the reasonable value of all services, labor and materials required, as set by the governing body. The fee herein shall be paid to the City Clerk upon obtaining a plumbing permit and the same shall be credited to the General Operating Fund of the city.
A copy of the plumbing permit shall be kept on the premises for public inspection during the performance of the work and until the completion of the same. The Plumbing Inspector may require a certified copy of the approved plans to be kept on the premises at all times from the commencement of the work to the completion thereof.
(a) When any plumbing is to be hidden from view by the permanent placement of parts of the building, the person, firm or corporation installing the plumbing shall notify the Plumbing Inspector and such equipment shall not be concealed until it has been inspected, approved or authorized by the Plumbing Inspector or until 24 hours, exclusive of Saturdays, Sundays and holidays, shall have elapsed from the time of such notification. On large installations, where the concealment of plumbing proceeds continuously, the person, firm or corporation installing the plumbing shall give the Plumbing Inspector due notice and inspections shall be made periodically during the progress of the work.
(b) The Plumbing Inspector shall have the authority to require owners or contractors to open such work which, in any manner, conceals plumbing that has been closed without his or her knowledge or permission, and in no case shall the Inspector issue a certificate of approval until satisfied that the work is in accordance with the provisions of this article. The Inspector shall also have the right to refuse to issue a certificate of approval on any plumbing, that is concealed in such manner that it cannot be fully determined that it has been done in accordance with this article.
(a) When the Plumbing Inspector finds plumbing construction to be in conformity with the provisions of this article, he or she shall issue to the person, firm or corporation performing the plumbing construction, a certificate of approval, with duplicate copy for delivery to the owner, authorizing the use of the plumbing system and connection to the supply of gas or water, as the case may be.
(b) When a certificate of approval is issued authorizing the connection and use of a temporary gas or water supply, the certificate shall expire at a time to be stated therein and shall be revocable for cause by the Plumbing Inspector.
(c) In no case shall certificates of approval be issued on plumbing or plumbing systems or parts of systems where the work installed does not conform to the requirements of this article.
(d) If, upon inspection, the plumbing or plumbing system is not found to be fully in conformity with the provisions of this article, the Plumbing Inspector shall immediately notify the person, firm or corporation making the installation of the existing defects.
(e) No certificate of approval shall be issued unless the plumbing or plumbing system has been installed in strict conformity with the provisions of this article and unless the plumbing or plumbing system is made in compliance with nationally approved methods of construction for safety to life and property as herein set forth.
(f) The Plumbing Inspector shall be deemed the judge of whether the plumbing or plumbing system has been made in accordance with the requirements of this article.
(g) No certificate of approval shall be required for making minor repairs of any plumbing including repair of leaks in water pipes, traps or cocks, opening up stoppage in waste or supply pipes, traps or drains, replacing fixtures when waste pipes are not disturbed, or replacing frozen pipes inside the building, and like repair work not involving original installation or reconstruction.
It shall be unlawful for any person, firm or corporation to make connection to a supply of gas or water for which an inspection is required, or which has been disconnected by the order of the Plumbing Inspector, until a certificate of approval has been issued by the Plumbing Inspector authorizing the connection and use of such plumbing or plumbing system. The Plumbing Inspector may, at his or her discretion, authorize a temporary connection.