A. Required; Notice: No connection with the city water mains shall be made without a permit being issued and twenty four (24) hours' notice having been given to the city clerk.
B. Costs: All such connections shall be made and all such work shall be done at the expense of the applicant who shall also furnish materials necessary for such work.
C. Supervision; Inspection: All such connection shall be made under the supervision of the city inspector or someone designated by the council, and no connections shall be covered until the work has been inspected by said inspector or his designee. (Ord. 136, 9-13-1990)
D. Application; Fee: Applications for such connections must be made to the clerk and such fee as determined from time to time by resolution of the city council shall be paid in advance. (Ord. 136, 9-13-1990; amd. 2008 Code)