§ 111.121 CLEANUP AND RESTORATION.
   (A)   (1)   (a)   The applicant shall conduct operations in an orderly fashion with continuous attention to the storage of equipment not in use, maintenance of the area, and the cleanup of trash and debris.
         (b)   The area used shall be cleaned of trash and debris within two hours of the completion of the activity or within such other time established in the permit to the village’s satisfaction.
      (2)   The applicant shall be responsible for restoring any area damaged or disrupted before leaving the site.
   (B)   (1)   If the site is not repaired or restored to the village’s satisfaction, the Village Manager or his or her designee shall have the necessary restoration and/or repairs performed and the applicant shall reimburse the village for such work within ten days of completing filming.
      (2)   In the event the applicant fails to so reimburse the village, the village may secure its reimbursement from either a cash or surety bond which shall be posted with the village to ensure faithful performance of such restoration.
   (C)   (1)   Such faithful performance bond shall be filed at the time of the application in the amount and in the manner provided for in § 111.115(F).
      (2)   The amount of the bond shall in no way limit the applicant’s liability or responsibility for the costs of repairs or restoration in the event those costs exceed the bond amount.
(1984 Code, § 8-13-120)