§ 51.07  SPRINKLER SYSTEMS.
   (A)   Permit required. No underground sprinkling device will be installed without a sprinkler installation permit issued by the city water master. The city water master will have final design approval of all new sprinkler system installations. No sprinkling system will be installed without a sprinkler installation permit and without adequate backflow prevention device(s) located at the point from which the water for irrigation is taken from the public water supply. The application for a sprinkler installation permit shall be obtained from the City Clerk’s office.
   (B)   Inspection of design plan. Upon receipt of the application, the city water master will inspect the design, order such changes as may be required to comply with this chapter and issue a sprinkler installation permit once the sprinkler system as built complies with this chapter.
(Ord. 05-18-15, passed 5-18-2015)  Penalty, see § 51.99