12-3-3: APPLICATION:
   A.   Prior to submittal of a formal subdivision application, the developer shall have completed a preapplication meeting with City staff to review the proposal. A developer seeking a preapplication meeting shall submit a copy of a concept plan to the Planning Department. A preapplication meeting will be scheduled at the earliest available date, upon receipt of the required conceptual plans and application by the City. The scope of the preapplication meeting shall include, but not be limited to:
      1.   The general subdivision process.
      2.   Overall design, lot sizes, and street layout.
      3.   Preliminary utility design.
      4.   Conformity to this Code, City standards, and policies.
      5.   Potential off site impacts/mitigations.
      6.   Off site/on site improvements.
Additional preapplication reviews may be scheduled when, in the collective judgment of staff, the proposed subdivision is extraordinarily complex, proposes large impacts to City infrastructure, or requires extraordinary staff time. When all issues have been adequately addressed, staff shall issue a written notice to proceed with subdivision application.
   B.   Following the completion of the preapplication meeting, a completed application for a subdivision plan approval may be submitted to and accepted by the City. Said application shall be on a form provided by the City. Along with the application the developer shall submit three (3) copies of the subdivision plan on eighteen inch by twenty seven inch (18" x 27") paper, one copy on eleven inch by seventeen inch (11" x 17") paper, and one copy on eight and one-half inch by eleven inch (81/2" x 11") paper. Details and specifications shall conform to the standards described in section 12-3-4 of this chapter and the Idaho Code.
Each application shall be accompanied by a fee in an amount to be established by the resolution of the Council. (Ord. 542, 1-27-2015)