13.08.070: OWNER'S RESPONSIBILITY FOR INSTALLATION:
The responsibility for installing the sewer service line from the municipal sewer lateral to the property connected shall be the responsibility of the owner and shall be done in accordance with the following conditions:
   A.   All sewer lines installed by the owner must be inspected by the village's representative before connection into the village lines is made. It is the responsibility of the owner to first obtain a connection permit and thereafter to notify the village when the service line is ready for inspection, such notice to be given at least twenty four (24) hours prior to the inspection. Any line backfilled without an inspection will not be accepted for service.
   B.   All pipe and fittings must be laid on undisturbed solid ground, or on a sand or clean gravel fill. Pipe shall be four inches (4") in diameter or greater, as required by the village.
   C.   All service lines must be either soil pipe, cast iron pipe, asbestos cement pipe, VCP or PVC with rubber gaskets. The asbestos cement pipe shall not be used in lengths in excess of five feet (5').
   D.   Cleanouts shall be installed by the owner on his property at every ninety foot (90') interval of line and at each bend or direction change of thirty degrees (30°) or more, extending into the property. Additional cleanouts may be required for larger than four inch (4") sewer service lines. Cleanouts shall consist of a standard combination Y and one-eighth (1/8) bend with standard riser and a four inch (4") brass cleanout plug. Cleanouts set out on a slope must be braced with timber.
   E.   Cement or concrete mortar or lead joints will not be permitted for jointing of any pipe, nor will the village permit encasing of the pipe or fittings with concrete, but all joints must be installed with rubber gaskets. (Ord. 177 § 7, 1976)