(A) It shall be unlawful for any person to discharge waste except as authorized by a permit issued under this chapter.
(B) A person applying for a new discharge shall:
(1) Submit an application on forms supplied by the approving authority;
(2) Secure approval by the approving authority of plans and specifications for the facilities when required;
(3) Comply with all requirements for agreements or arrangements including but not limited to, provisions for:
(a) Payment of charges;
(b) Installation and operation of the facilities and of pretreatment facilities, if required; and
(c) Sampling and analysis to determine quantity and strength when directed by the city; and
(4) Provide a sampling point, when requested by the city, subject to the provisions of this chapter and approval of the approving authority.
(Ord. 2011-01, passed 1-25-11) Penalty, see § 53.99