[Added 10-10-1988 by Ord. No. 20-1988]
Should any applicant reserve capacity and pay the fees under § 223-8 hereof and receive permission to commence construction with dry connections and should said individual fail to pay the annual maintenance fee as required by § 223-8E for any period between the time that capacity is reserved and that the individual is able to hook up after the removal of the ban on hookups to the Hammonton Sewer Treatment Plant, said individual shall not be permitted to hook up to the sewer treatment plant until all fees covering the interim period from the year when reservation of capacity first occurred and including that year in which the right to hook up is requested. The Sewer Superintendent shall not permit the hookups unless a certification is received from the Town Clerk/Administrator evidencing the fact that all payments of the annual fees for reservation of capacity under § 223-8 have been made.