§ 53.019 RESPONSIBILITY FOR IMPLEMENTATION.
   A project site owner shall be identified for all projects that require the submission of a stormwater pollution prevention plan (SWPPP) and a construction permit per § 53.016(A).
   (A)   The project site owner has the following responsibilities:
      (1)   Ensure that a sufficient SWPPP is completed, submitted and approved by the Division of Stormwater Management (DSM);
      (2)   Complete a sufficient notice of intent (NOI) letter to be submitted to the Indiana Department of Environmental Management (IDEM), with a copy sent to the DSM and HDEM;
      (3)   Make application and obtain a land disturbance permit in accordance with procedures established by the DSM;
      (4)   Ensure compliance with this subchapter during:
         (a)   The construction activity; and
         (b)   Implementation of the construction plan;
      (5)   Ensure that all persons engaging in construction activities on a permitted project site comply with the applicable requirements of this rule and the approved SWPPP; and
      (6)   Notify the IDEM with a sufficient notice of termination (NOT) letter with a copy sent to the DSM and HDEM.
   (B)   For an individual lot where land disturbance is expected to be 1 acre or more and the lot lies within a project site permitted under this rule, the individual lot owner shall:
      (1)   Ensure that a sufficient stormwater management construction plan has been submitted to and approved by the DSM and a construction permit has been obtained;
      (2)   The stormwater management plan and construction activity shall comply with the technical standards adopted by the BSM and with all sections of this subchapter and be in accordance with the applicable procedures established by the DSM;
      (3)   Complete his or her own sufficient notice of intent (NOI) letter to be submitted to the Indiana Department of Environmental Management (IDEM), with a copy sent to the DSM and HDEM; and
      (4)   Notify the IDEM with a sufficient notice of termination (NOT) letter with a copy sent to the DSM and HDEM.
   (C)   For an individual lot where the land disturbance is less than 1 acre and the lot lies within a project site permitted under this rule, the individual lot operator shall:
      (1)   Comply with the provisions and requirements of the DSM approved SWPPP and the stormwater construction permit for the overall site, comply with the technical standards adopted by the BSM and comply with this subchapter. All work shall be performed in accordance with the applicable procedures established by the DSM; and
      (2)   A NOI is not required.
(Ord. 8970, passed 12-8-2008)