15.16.120.09: PERMITS ISSUED PRIOR TO EFFECTIVE DATE:
Notwithstanding any other provision of this chapter, that portion of a project for which a complete application for a building permit has been received by the city prior to the effective date hereof shall not be subject to the development impact fees imposed by this chapter. If the resulting building permit is later revised or replaced after the effective date hereof, and the new building permit reflects a development density, intensity, development size or number of units more than ten percent (10%) higher than that reflected in the original building permit, then development impact fees may be charged on the difference in density, intensity, development size or number of units between the original and the revised or replacement building permit. (Ord. 985 § 1, 2007)