§ 154.155 APPROVAL PROCESS.
   (A)   Determination of completeness. An application for a tower shall be filed with the Town Manager. The Town Manager shall review the application for completeness and notify the applicant in writing if the application is incomplete. The notice shall describe any deficiencies.
      (1)   If the application is for collocation on an existing structure, notice of incompleteness shall be given within ten days of the date of the application.
      (2)   If the application is for placement of an antenna on a new tower, notice of incompleteness shall be given within 30 days of the date of the application.
      (3)   If the application is for a new monopole, notice of incompleteness shall be given within 60 days of the date of the application.
   (B)   Approvals. All approvals shall be complete within the following time frames unless tolled by a notice of deficiency:
      (1)   For collocation on an existing structure, 60 days of the date of the application.
      (2)   For an application for an antenna on a new structure, 90 days of the date of the application.
      (3)   For a new monopole, 150 days from the date of the application.
   (C)   Final decision. Any final decision to approve or deny a request shall be in writing and set forth the reasons and substantial evidence for the decision.
(Ord. O2020.26, passed 8-27-2020)