CHAPTER 907
Streets
907.01    Specifications.
907.02    Required improvements.
907.03    Bonds.
907.04    Backfill.
907.05    Application.
907.06    Cutting or trimming of trees.
907.99    Penalty.
 
CROSS REFERENCES
Power to establish and care for streets - see Ohio R.C. 715.19, 717.01, 723.01
Openings by the Municipality - see Ohio R.C. 723.02
Sprinkling - see Ohio R.C. 723.16 et seq.
Surface treatment - see Ohio R.C. 723.23, 723.31
Excavation liability - see Ohio R.C. 723.49 et seq.
Changing established grade - see Ohio R.C. 727.07
Digging, excavating and piling earth on street - see Ohio R.C. 5589.10
 
907.01 SPECIFICATIONS.
   All new streets constructed in the City, after the effective date of this section shall have combination concrete curb and gutter with I-4 under drain including porous backfill, a base course of stone or Portland cement and a surface course of asphaltic concrete as shown on and by the minimum requirements for the improvement of streets in the City Subdivision Regulations. Such requirements are on file with the Clerk of Council of the City and the City Planning and Zoning Commission.
(Ord. 370. Passed 3-3-56.)
907.02 REQUIRED IMPROVEMENTS.
   Before any new street is constructed in the City, the following shall be installed in the street right of way: sanitary sewers; storm sewers; water lines; gas lines and laterals from all the above mentioned utilities to the lot lines of any lots fronting on such new streets.
(Ord. 370. Passed 3-3-56.)
907.03 BONDS.
   (a)    Before the construction of any street in the City, the person, firm or corporation intending to construct the street or streets shall, prior to construction, deposit with the Finance Director a bond acceptable to the City or a certified check guaranteeing the completion of the street improvement within one year or such time as may be agreed to by Council. The bond or check shall be in an amount equal to the estimated cost of constructing the street improvements and as approved by Council. A maintenance bond in the amount of five percent (5%) of the preliminary estimated or final construction cost shall be provided for maintenance of the street for a period of one year after the date of acceptance of the street improvements by Council.
   (b)    Such bonds or certified cheeks shall inure to the benefit of the City to be used by the City to complete the street or streets in accordance with this chapter in the event that the person, firm or corporation attempting to construct the street or streets does not comply herewith. (Ord. 576. Passed 7-26-65.)
907.04 BACKFILL.
   Whenever it is necessary to excavate any portion of a new street, the excavation shall be filled with grits, and no earth shall be used to fill such excavation.
(Ord. 370. Passed 3-3-56.)