(A) Solar Energy Systems (SES) will be required to have a City of Greenville building permit. Solar energy systems constructed before a building permit has been issued will be charged double the permit fee. A written plan and a plat/drawing for the proposed solar energy system shall be provided with the building permit application. The plat /drawing must show the location of the system on the building or on the property, with all property lines and setbacks indicated.
(B) Fees for processing the application for building permits shall be submitted to and collected by the City of Greenville as follows:
Fees Below
|
Fees Below
| |
0-10 kW | $50 |
11-50 kW | $75 |
51-100 kW | $750 |
101-500 kW | $2,000 |
501kW-1 MW | $4,000 |
1 MW-2MW | $6,000 |
over 2 MW | $6,000 plus $200 each add’l 100 kw or $2,000 per each additional MW |
(C) A one-time application fee will be assessed at the time the application is filed.
(Ord. 3309, passed 9-12-2023)