1440.10   TIME EXTENSION.
   The holder of a permit may apply to the Zoning Board of Appeals for an extension of the time limits stated in Section 1440.09. The permit holder shall be required to file an application with the Secretary of the Board ten days prior to the expiration date of the permit and shall state in the application the reasons why he was unable to commence or complete construction within the required time limits. If an extension of time is approved, the Board shall notify the Zoning Inspector as to the length of time the Board has given the permit holder to commence or complete the construction. If the Board disapproves the extension of time, the permit shall be revoked when the time limits expire.
(Ord. 95-18. Passed 2-7-95.)