3-1-23: CONTRACT CHANGES:
Every contract modification, change order or contract price adjustment in excess of ten thousand dollars ($10,000.00) and every contract modification, change order or contract adjustment extending the contract completion time under a contract for the construction of a public improvement with the Village shall be subject to prior approval by the Board of Trustees after receiving a report from the project manager as to the effect of the contract modification, change order, or contract price adjustment on the total project budget or the total contract budget. (Prior ord.)