(A) The contractor executing the excavation must properly notify all affected utilities prior to commencing any work; i.e., notify Diggers Hotline.
(B) In making excavations in streets, alleys, highways or easements for laying service pipe or making repairs, the paving and earth removed must be deposited in a manner that will occasion the least inconvenience to the public.
(C) No person shall leave such excavation made in any street or highway open at any time without barricades; and during the night, warning lights must be maintained at such excavations.
(D) In refilling the opening, after the service pipes are laid, the earth must be laid in layers of not more than nine inches in depth, and each layer thoroughly compacted to prevent settling. This work together with the replacing of sidewalks, gravel and paving, must be done so as to make the street as good, at least, as before it was disturbed and satisfactory to the village. No opening of the streets for tapping the pipes will be permitted when the ground is frozen.
(Ord. passed 9- -2011) Penalty, see § 52.99