(a) A permit will be considered invalid if work has not started within twelve (12) months of the date of issuance.
(1) At the request of the applicant, a permit may be renewed for an additional twelve (12) month period if requested at least 10 days prior to expiration, and upon collection of the appropriate fee.
(b) A permit will be considered invalid if work is delayed or suspended for more than six (6) months.
(1) At the request of the applicant, a permit may be renewed twice for an additional six (6) month period if requested at least 10 days prior to expiration, and upon collection of the appropriate fee.
(Ord. 2013-22. Passed 4-9-13.)