925.18 INSPECTIONS.
   (a)   Approval Required. No building sewer or building sanitary sewer shall be covered or placed in service until it has been approved by the Director of Water/Sewer and a signature indicating the approval has been issued.
   (b)   Final Inspection; Certificate of Approval. All work covered by this chapter shall be submitted for final inspection and approval. If the sewer tapping work is found to be complete and in conformity with all provisions of this chapter and if all street pavements or surfaces removed as part of the work have been acceptably repaired, a certificate of approval shall be issued by the Chief Building Inspector.
   (c)   Incompleteness or Nonconformity; Corrections; Stop Work Order. When inspection shows work submitted for inspection is incomplete or not in conformity with requirements of this chapter, the permit holder shall make the necessary corrections or additions within seventy-two hours and resubmit the work for inspection. Failure to correct rejected work shall be cause for issuance of a stop work order on the entire project or for suspension or revocation of permit.
   (d)   Inspection Fee. The fee for inspection as provided for in this section shall be twenty-five dollars ($25.00).
(Ord. 90-5835. Passed 8-14-90.)