(A) The construction of the storm water storage area and/or storm water passageway shall be under the supervision of an Illinois registered professional engineer. He shall be responsible for all construction in accordance with approved plans.
(B) In addition, a registered engineer employed by the city may inspect all drainage facilities while under construction. When facilities are not constructed according to approved plans, the city has the explicit authority to compel compliance and require correction of any situations which are not according to the approved plans. A set of as-built plans shall be submitted to the Building Official for his approval upon satisfactory completion of the construction of the storm water storage area and/or excess storm water passageway. In addition to the as-built plans, the design engineer shall provide written verification that, as constructed, the basin meets the requirements of the city's storm water detention ordinance.
('69 Code, § 5-18(b)(8)) (Ord. O-83-1, passed 5-9-83; Am. Ord. O-03-43, passed 12-8-03)