§ 12.5-871 PLACEMENT OF FILL MATERIAL IN EXISTING OR PROPOSED RIGHTS-OF WAY.
   Prior to the city infrastructure inspection, fill material placed in any existing or proposed dedicated right-of-way should be tested and certified by an independent soils laboratory to show that it meets the requirements of the City of Fort Worth Standard Specifications for Street and Storm Drain Construction. If testing and certification is not performed prior to a city infrastructure inspection, the city may require testing and certification by an independent soils laboratory and/or removal of the fill material.
(Ord. 15789, § 1, passed 12-9-2003)