The placement or import of the fill material must meet the following conditions:
(a) The purpose of the fill material is to make the land suitable for the construction of surface improvements;
(b) The fill material shall not be higher than the highest elevation along the perimeter of the adjacent tracts, parcels or platted lots, however; fill material placed on pad sites shall not exceed three feet in height above the highest elevation along the perimeter of the adjacent tracts, parcels or platted lots;
(c) The slope of the fill material is a maximum ratio of three feet horizontal to one foot vertical, unless a retaining wall system built in compliance with the city code and regulations is in place; and
(d) Fill material must be leveled and graded for positive drainage no less than every 30 days.
(Ord. 15789, § 1, passed 12-9-2003)