All land-disturbing activities:
(A) Limit both on-site and off-site annual soil losses during the period of construction and revegetation to the amount agreed upon by the permit issuing authority or responsible unit of government;
(B) Construction areas shall be seeded with adapted grasses or temporary cover crop within 14 days after construction activity is required in critical erosion areas. Protection measures will be applied to all construction areas. The disturbed areas will be seeded to adapted grasses or a temporary cover crop within 14 days after the construction activity is completed under normal weather conditions; and
(C) Areas needing protection will be mulched when construction is completed during the non- growing season.
(Prior Code, § Q-11-106) (Ord. 989, passed - -) Penalty, see § 159.999