(A) The following standards shall apply to dwelling units and all commercial and industrial projects and larger connecting to the city distribution system. The interpretation of any section, or of any difference in sections, when appropriate, shall be made by the City Manager or designee. This interpretation shall be binding and controlling in its application. Before any connection is made to any structure under this section it shall be required that a site plan be submitted indicating exterior proposed taps, connections, and valves.
(B) A load profile or an estimate from the customer’s engineer shall be submitted to assist the city in properly selecting and sizing the meter (above a standard five-eighths inch household meter) for the proposed facility. A
LOAD PROFILE is defined as a written or graphical estimate of the average and peak gallon consumption for each hour of a 24-hour period.
(C) If large seasonal flow fluctuations are anticipated, a load profile must be submitted for each season of the year. The type of meter installed will be based upon size, service requirements, location of meter, and other conditions which may exist. Property owners or developers are to adequately size water lines to their building units.
(Ord. D-20, passed 10-21-2014)