§ 155.403 PROCESSING OF APPLICATION.
   (A)   Applications will be reviewed for substance only when they meet all submittal requirements. If applications are not complete, staff must notify the applicant within ten days from the submission of the application stating the application is incomplete and identifying the missing materials, which must be submitted in order to complete the application. No further review of the application will take place until the application is complete. If the resubmitted materials are not complete, staff must notify the applicant within ten days from the submission of the application stating the application is incomplete and identifying the missing materials, which must be submitted in order to complete the application. No further review of the application will take place until the application is complete.
   (B)   For applications that are eligible for administrative review and approval, staff shall review and take final action on applications for new small cell systems within 30 days of a completed application. This time period will not begin until the application is deemed complete by staff. Staff shall notify the applicant once the application is deemed complete and provide the deadline for the staff review period. Staff shall either approve, approve with conditions, or deny the application. If staff does not make a final decision within the required 30 days, the application shall be deemed to be approved as submitted.
   (C)   (1)   An applicant claiming to be injuriously affected or aggrieved by an official action, order, requirement, interpretation, grant, refusal, or decision of staff in the administration of these regulations may appeal the action to the Board of Zoning Adjustments pursuant to § 155.051 of the Zoning Ordinance.
      (2)   An applicant claiming to be injured or aggrieved by any final action of the Planning Commission or Board of Zoning Adjustments shall appeal from the final action to the Franklin County Circuit Court. Such appeal shall be taken within 30 days after such action, or such longer period as allowed under applicable law.
   (D)   The procedure by which the Planning Commission may allow for waivers of these regulations is set out in § 155.008 of the Zoning Ordinance.
   (E)   In addition to Planning Commission approval, any applicable building, zoning, and electrical permits, and permission from the local jurisdiction, right-of-way or property owner are required prior to the beginning of construction.
(Ord. 10-2021, passed 8-12-2021)