(a) All applications for new ground mounted wireless telecommunication facilities or for wireless telecommunications facilities located on structures that have not previously supported wireless telecommunications facilities shall be considered special approval uses and shall be required to obtain special approval as described in Section 1268.32.
(1) After an application for special approval review has been filed with the Village, Village staff or consultants shall have 14 days to determine whether the application is complete. If, in those 14 days, the Village determines that the application is incomplete and notifies the applicant of the deficiencies, the applicant shall fulfill all deficiencies.
(2) If the Village fails to notify the applicant that the application is not complete within 14 days, then the application shall be deemed complete and the Village Council shall have 90 days to approve or deny the application. If the Village Council has not acted within 90 days, the application will be deemed approved.
(3) When the application is complete, the Village Council shall have 90 days to approve or deny the application. If the Village Council has not acted within 90 days, the application will be deemed approved.
(b) All applications to modify existing wireless telecommunications facilities, or to co-locate a wireless telecommunications facility on a structure with an existing wireless telecommunication facility, shall be reviewed administratively by Village staff or consultants.
(1) After an application for a modification or co-location has been filed with the Village, Village staff or consultants shall have 14 days to determine whether the application is complete. If, in those 14 days, the Village determines that the application is incomplete and notifies the applicant of the deficiencies, the applicant shall fulfill all deficiencies. If the Village fails to notify the applicant of deficiencies with 14 days, then the application shall be deemed complete.
(2) When the application is complete, the Village shall have 60 days to issue an approval of the application. If the Village has not acted with 60 days, the application will be deemed approved.
(c) Application fees for wireless telecommunications facilities of any type shall not exceed one thousand dollars ($1,000.00).
(Ord. 2013-10. Passed 10-14-13.)