§ 50.41  NET METERING.
   (A)   The findings and determinations set forth in the Preamble to Ordinance10-03 are hereby made findings and determinations of the Council.
   (B)   The city encourages interested citizens and businesses to invest in renewable electric energy generation systems and enter into a net metering program with the municipal electric utility of the city.
   (C)   Eligible net metering customers include residential, commercial and industrial customers in good standing that own and operate a solar, wind, biomass, geothermal or hydroelectric generating facility that:
      (1)   Has a nameplate capacity less than or equal to ten kilowatts(kw);
      (2)   Is located on the customer's premises and is operated by the customer; and
      (3)   Is used primarily to offset all or part of the customer's own electricity requirements.
   (D)   The Council authorizes the utility to offer net metering to eligible net metering customers on a first come, first served basis.  The utility shall limit the aggregate amount of net metering facility nameplate capacity from all net metering customers to 0.1% of the utility's most recent summer peak load.
   (E)   The utility shall measure the difference between the amount of energy delivered by the utility to the net metering customer and the amount of energy generated by the net metering customer and delivered to the utility.  If the net metering customer generates more energy than it consumes in a month, the customer shall receive a bill credit from the utility for the amount of surplus energy generated.  The utility shall not purchase or wheel power produced by an eligible net metering customer's facilities.
   (F)   The Net Metering Tariff attached to Ordinance 10-03 and incorporated herein by reference shall be adopted as the terms and conditions under which the utility will offer net metering to eligible net metering customers.
   (G)   In accordance with the Net Metering Tariff, the utility shall enter into an interconnection agreement with the eligible net metering customer prior to connecting the customer's net metering equipment to the utility's system.  The connection agreement shall incorporate technical interconnection requirements and applicable provisions of the Net Metering Tariff, and shall not be in conflict with the terms of this section.
(Ord. 10-03, passed 3-22-10)