§ 152.177 FINAL DEVELOPMENT PLAN APPLICATION.
   (A)   Within 12 months of the Village Council's approval of the PUD District, including the preliminary development plan, the applicant shall submit a request to the Zoning Administrator for final PUD approval. If the project includes phases, then the applicant must submit a request within 12 months of the Village Council's approval of the PUD District for final approval of any phase.
   (B)   If the applicant fails to submit a request within 12 months as stated above, then the preliminary site plan (not the PUD rezoning) shall be determined to be invalid. If a preliminary plan includes phases, the applicant must submit each subsequent phase within 24 months of the approval date of the initial phase. If the applicant fails to submit the next phase within this time period, then the preliminary site plan incorporating all phases not approved for final site plan shall be determined to be invalid. Upon request to the Village Council and in accordance with § 152.182(A)(1) and (A)(2), the time frames may be extended for a reasonable period of time.
   (C)   A final development plan application shall consist of the following:
      (1)   A completed application form, supplied by the Zoning Administrator.
      (2)   Payment of a fee, as established by the Village Council.
      (3)   A written response to the findings, review comments, and conditions, if any, from the Village Council's review and approval of the preliminary development plan and a narrative explanation of the changes made to the plan in response to those items.
   (D)   A site plan containing all of the information required in this PUD subchapter and as stated in §§ 152.190 through 152.195, under final site plan review, § 152.192(B)(2)(a). If the plan consists of phases, then the above mentioned information is only required for the specific phase(s) being presented for final approval. Each subsequent phase shall be reviewed in the same manner.