(A) Following the pre-application conference, applicants seeking approval of a PUD District shall submit a complete application for review to the Zoning Administrator who shall schedule a date and time for a public hearing and Planning Commission review. Such application shall include the following:
(1) A completed application form, supplied by the Zoning Administrator.
(2) Payment of a fee, as established by the Village Council.
(3) A narrative statement describing:
(a) The objectives of the PUD and how it relates to the intent of the PUD District, as described in § 152.170.
(b) The relationship of the PUD to the Village of Fowler Master Plan (if the village develops a Master Plan).
(c) Phases of development and approximate time frame for each phase.
(d) Proposed deed restrictions, covenants, or similar legal instruments to be used within the PUD.
(e) Anticipated start and completion of construction.
(f) Location, type, and size of areas to be dedicated for common open space.
(B) Sufficient copies of a preliminary development plan shall be provided to the Zoning Administrator. If the PUD is to be developed in phases, the preliminary development plan shall show all phases. The preliminary plan shall contain the same information required in §§ 152.190 through 152.195, under site plan review procedures, § 152.192(B)(1)(b).
(C) Upon receipt of an application for PUD approval, the Zoning Administrator shall cause notice to be given, in accordance with the PUD rezoning requirements of the Zoning Act.