If the city determines that the project is not being carried out in accordance with the approved plan, or that any project subject to this chapter is being carried out without approval, the Building Official, after notifying the City Council in writing, is authorized to:
(A) Issue a stop-work order directing the applicant or owner to cease and desist all or any portion of the work which violates the provisions of this chapter;
(B) Issue written notice to the owner specifying the nature and location of the alleged noncompliance, with a description of the remedial actions necessary to bring the project into compliance within a reasonable specified time; and/or
(C) Should the applicant or owner not bring the project into compliance with the written notice and stop-work order, he or she shall then be subject to immediate revocation of his or her building permit and to the penalties described in § 10.99.
(`95 Code, § 5-8-27) (Am. Ord. 35-19, passed 1-14-20)