1311.10 ELECTRICAL PERMIT FEES.
   Fees for electrical permits shall conform to the following table:
Processing/Application Fee
$15.00
Special Inspection Fee (survey fees/fire damage)
30.00/hour
Additional Three percent (3%) pursuant to Ohio Building Code for Commercial projects:
Additional One percent (1%) pursuant to Residential Code of Ohio for Residential projects:
Service
Fee (Each)
New Service/Change/Reconnect - 60 - 200 amp
20.00
New Service/Change/Reconnect - 201 - 400 amp
25.00
New Service/Change/Reconnect - 401 - 1000 amp
35.00
New Service/Change/Reconnect - 1,001 amp & up
55.00
Residential Pre-heat Service Release
20.00
Alteration/Repairs (each 10 openings)
20.00
Additional sub-service/meter (each)
20.00
Sub-panels (each)
20.00
Temporary Pole (each)
20.00
Trench/Ceiling/Slab (each)
20.00
Rough Inspection
20.00
Final Inspection
20.00
2 wire circuit/Feeders (each)
2.50
3 wire circuit/Feeders (each)
2.50
Pool (Above ground)
25.00
Pool (In ground)
50.00
Transformers/Generators (each)
25.00
Motor/Starters/Disconnects (each)
5.00
Re-inspection Fee
20.00
Commercial Electric Plan Review
(current hourly rate)