This section establishes procedures for an applicant to request a change to an approved project.
(A) Request for a change. An applicant must request changes in writing, with appropriate supporting materials and an explanation for the request.
(B) Major changes. A major change to an approved project means any change that does not qualify as a minor change under division (C) below. Major changes must be approved by the same review authority as the original approval. The same public notice and hearing requirements that applied to the original approval also apply to the requested major change.
(C) Minor changes.
(1) The Director may authorize minor changes to an approved project if the changes:
(a) Are consistent with the Zoning Code;
(b) Are consistent with the spirit and intent of the original approval;
(c) Do not involve a feature of the project that was a mitigation measure or a basis for findings in a negative declaration, mitigated negative declaration or environmental impact report for the project;
(d) Do not involve a feature of the project that was a basis for conditions of approval for the project;
(e) Do not involve a feature of the project that was a specific consideration by the review authority in granting the approval; and
(e) Do not involve any expansion, intensification or increase in size of the land use or structure beyond the original approval.
(2) The Director may approve minor changes without a noticed public hearing.
(Ord. 885-C.S., passed 5-21-19)