§ 50.053 WASTEWATER DISCHARGE PERMIT DECISIONS.
   The City Manager will evaluate the data furnished by the industrial user and may require additional information. Within 45 days of receipt of a complete wastewater discharge permit application, the City Manager will determine whether or not to issue a wastewater discharge permit. If no determination is made within this time period, the application will be deemed denied. The City Manager may deny any application for a wastewater discharge permit.
('63 Code, § 5-5.408) (Ord. 571-C.S., passed 7-2-94; Am. Ord. 775-C.S., passed 12-20-11)