931.11 FEES.
   The SWP3 and Abbreviated SWP3 review, filing, and inspection fee is part of a complete submittal and is required to be submitted to the City of Euclid and the Cuyahoga SWCD before there view process begins. Please consult with City of Euclid Engineer for current fee schedule.
   Applicants will be charged $250 for each additional inspection that Cuyahoga SWCD must conduct a site has one of the following compliance issues:
   (a)   Construction activities have started at the site with no SWP3 completed;
   (b)   Failure to install sediment basin(s) when the SWP3 and/or site drainage clearly indicate as a first step (within 7 days prior to grading and within 7 days of grubbing);
   (c)   Failure to implement any sediment/erosion controls; or
   (d)   Dewatering activities resulting in turbid discharges.
(Ord. 18-2022. Passed 2-22-22.)