1391.10  TIME TO COMPLETE DEMOLITION.
   Demolition work shall be completed within thirty days from the date of the commencement except that in the case of unusual conditions prohibiting completion, the Building Inspector may allow an additional thirty days for the work to be completed.
   Cleaning up of premises shall be accomplished within the time allotted for the work to be done.
(Ord. 4878.  Passed 9-16-57; Ord. 2001-38.  Passed 3-5-01.)