§ 155.05 EROSION PREVENTION AND SEDIMENT CONTROL PLAN.
   (A)   The EPSC plan shall include the following:
      (1)   A natural resources map identifying soil types, forest cover, topography and other natural features of concern. This map should be to scale equivalent to balance of submittal;
      (2)   A schedule of events for the construction of the development site, including stripping and clearing, rough grading, construction of utilities, infrastructure, final grading and landscaping. Sequencing shall identify the expected date on which clearing will begin, the estimated duration of exposure of cleared areas, areas of clearing, installation of temporary EPSC measures and establishment of permanent vegetation;
      (3)   All EPSC measures necessary shall be shown on the plan by location and referred to by a legend for all phases of construction. Depending upon the complexity of the project, the drafting of interim plans may be required at the close of each season. Multiple EPSC plan sheets may be necessary to best convey requirements for each phase;
      (4)   Seeding mixtures and rates, types of sod, method of seedbed preparation, expected seeding dates, type and rate of lime and fertilizer application and type and quantity of mulching for both temporary and permanent vegetative control measures; and
      (5)   Provisions for maintenance of control facilities, including easements and estimates of the cost of maintenance.
   (B)   Modification to the plan shall be processed and accepted or denied in the same manner as § 155.04 of this chapter and authorized by the city by written authorization to the permittee, and shall include:
      (1)   Major amendments of the EPSC plan shall be submitted to the city for acceptance; and
      (2)   Field modifications of a minor nature shall require authorization by the city and shall be noted and dated on the EPSC record drawings. Where minor modifications prove to be ineffective, the EPSC contractor shall return to the intent of the original plan within seven days of notification by the inspector.
(Prior Code, § 157.05) (Ord. 01-2007, passed 3-5-2007)